How to compare contractor estimates line by line

Compare contractor estimates line by line: match scope, materials, quantities, permits, cleanup, schedule, payment terms and warranty before you choose.

The short answer

To compare contractor estimates, give every company the same description of the job, then line the bids up item by item: scope, materials by brand and model, quantities, permits, cleanup, schedule, payment terms and warranty. Don't just pick the lowest total. When bids differ a lot, ask each contractor to explain why, since the gap usually comes from something one bid includes and another leaves out.

Key points

  • Bids only compare fairly if every contractor priced the same scope.
  • A good estimate describes the work, materials, completion date and price, on the company's letterhead.
  • Check what's missing as well as what's listed: permits, disposal, cleanup and allowances.
  • Treat a bid far below the rest with caution, and ask why it's lower.
  • A contractor can't legally offer to waive or absorb your insurance deductible in a bid.

How to compare contractor estimates line by line

When you compare contractor estimates, the totals are the least useful part. The FTC says not to automatically choose the lowest bidder and to ask for an explanation when estimates differ widely. The difference is almost always in the details: one bid includes the permit, another leaves out disposal, a third uses cheaper materials.

This guide walks through how to set up your bids so they can be compared, what each one should show, and how to read them side by side.

Start by giving everyone the same scope

Before you ask for bids, write down what you want done: the areas involved, what's being removed, what's going in, and any brands or finishes you've already chosen. Give the same notes to every contractor.

If a contractor suggests something different, like a different material or an extra step, ask them to price your version and their version separately. That keeps your comparison honest and still lets you learn from their suggestion.

What every estimate should show

The FTC says a written estimate should include a description of the work, the materials, the completion date and the price. The Texas Department of Insurance adds that bids should be on the company's letterhead, with its phone number and address, and that you should keep copies of every agreement and warranty.

If an estimate is a single number on a business card, ask for a written, itemized version. You can't compare what you can't see.

The line items to compare side by side

Make a simple table with one column per contractor and one row for each of these. Blank cells are where the questions are.

  • Scope: every task listed, including demolition and prep.
  • Materials: brand, model, size and color, as the FTC suggests for contracts. Same price for a different grade isn't the same price.
  • Quantities: square feet, linear feet or number of units. If one bid has noticeably more or less, ask how they measured.
  • Allowances: budget amounts for items you'll choose later, like fixtures or tile. A low allowance can make a bid look cheaper than it will end up.
  • Permits: who pulls them and whether permit costs are included. Inside Fort Worth, the city lists many jobs that need one, from replacing exterior windows and doors to electrical, plumbing and HVAC work.
  • Subcontractors: which parts of the job each company will sub out, and to whom.
  • Disposal and cleanup: hauling away debris and a broom-clean finish, which the FTC suggests putting in writing.
  • Schedule: start date, completion date, and how long the job will take.
  • Payment terms: deposit, progress payments and final payment.
  • Warranty: what's covered, who honors it, and for how long.
  • Exclusions: anything the bid says it doesn't cover.

TipAsk each contractor how they'll price changes once work starts, for example a set rate or a written quote for each change order. A bid that's low up front can become expensive through changes.

Example: comparing roof estimates in Fort Worth

Roofs show why line items matter. Fort Worth's roofing FAQ says replacing only shingles on a one- or two-family home doesn't need a permit, but replacing any decking does. So check whether each bid includes decking replacement, how it's priced, and whether the permit is included if decking is replaced.

The city's roofing FAQ also says that during a re-roof, drip edges and crickets are required where none exist, and that underlayment must meet the shingle manufacturer's instructions or the residential code, whichever is stricter. If one bid lists drip edge and another doesn't, ask why. These rules apply inside Fort Worth city limits; nearby cities such as Arlington, Keller or Benbrook set their own, so check with your city.

If insurance is paying, the Texas Attorney General suggests having your adjuster estimate the damage and repair cost first. That professional estimate gives you a benchmark for comparing contractors.

When one bid is much lower than the rest

A much lower bid isn't automatically a bargain. The Texas Department of Insurance says to be careful if one bid is much lower than the others, and the Attorney General warns about low-ball estimates after disasters. Before you take the cheapest one, find out what it leaves out.

Watch for one particular trick on insurance jobs. The Texas Department of Insurance says contractors can't offer to waive your deductible or include it in a bid. One way it's done is an estimate written higher than the real repair cost, so the extra insurance money covers your deductible, and TDI calls inflating repair costs for your insurer fraud. If a bid looks low because it absorbs your deductible, find another contractor and report it to the Attorney General at 800-621-0508.

Questions to ask before you choose

  • Why is your price higher or lower than the others I've received?
  • What exactly is included in this line, and what isn't?
  • Which materials, by brand and model, are you pricing?
  • Will you pull the permit, and is the fee in this price?
  • Who will be doing the work, your crew or subcontractors?
  • What will you charge if you find hidden damage once work starts?
  • What warranty do you give on your workmanship, and is it in writing?

Once you've picked a bid, make sure the contract matches it line for line. Cowtown Pros ranks local companies on what their own websites show, which can help you decide whom to ask for bids, but the itemized estimate is what tells you who's actually offering the better deal.

FAQs

How many estimates should I get?

The FTC suggests getting estimates from several firms. Enough to see a pattern matters more than a specific number, as long as each bid prices the same scope.

Should I always pick the lowest bid?

No. The FTC says not to automatically choose the lowest bidder, and TDI says to be careful if one bid is much lower than the rest. Ask what the low bid leaves out.

Why are my contractor quotes so different?

Usually because they're pricing different things: different materials, quantities, allowances, or whether permits, disposal and cleanup are included. Line the bids up item by item and ask each contractor to explain the gaps.

Can a contractor include my insurance deductible in the bid?

No. TDI says it's illegal in Texas for a contractor to offer to waive, rebate or absorb your deductible.

Sources

Every rule and figure in this guide comes from one of these pages, which we read in November 2026. Rules change, so check the agency's own page before you rely on it.

  1. FTC: How To Avoid a Home Improvement Scam
  2. FTC: Hiring a Contractor (2014 publication)
  3. Texas Department of Insurance: How to avoid contracting scams
  4. Texas Department of Insurance: Is it OK for a contractor to waive my deductible?
  5. Texas Attorney General: Disaster Scams
  6. City of Fort Worth: Roofing FAQ
  7. City of Fort Worth: Residential Permitting

See something wrong or out of date? Request a correction